WDEQ’s contractor (WWC Engineering) completed field data collection for the site assessment in June 2020. To date, 80 soil samples, 8 river sediment samples, 4 quarters of surface water samples from 3 sampling locations, and 4 quarters or groundwater samples from 10 sa...

April 15, 2020

The Sheridan County Conservation District was awarded a $2500 grant from the Wyoming Community Foundation through the Sheridan-Johnson Community Foundation Endowment Fund.  The grant will be used to support outreach efforts associated with the Acme Power Plant Reclamat...

January 28, 2020

The Acme Working Group is hosting a public meeting to provide an update on recent and upcoming activities at the former Acme Power Plant.  The meeting will begin at 6:00 pm at the Sheridan County Fulmer Public Library Inner Circle on Thursday February 6.  Presenters wi...

January 29, 2019

SCCD is requesting cost proposals for field surveys and necessary applications/paperwork for a road easement and a water right change of point of diversion at the Acme site. The deadline for submission is March 1, 2019. 

January 11, 2019

The Acme Working Group is hosting a public meeting to provide an update on recent and upcoming activities at the former Acme Power Plant.  The meeting will begin at 6:30 pm at the Downtown Sheridan Memorial Hospital Conference Center at 61 South Gould Street on Thursda...

Please reload

Archive
Please reload

Proudly created with Wix. com

© 2018 by Acme Power Plant Reclamation Project.

c/o Sheridan County Conservation District

1949 Sugarland Drive, Suite 102

Sheridan, WY  82801

(307) 672-5820 x. 3

Please respect fences and adjacent landowners by not attempting to enter the site. Anyone accessing the site (legally and illegal trespassers) has the potential to track contaminants to surrounding areas and/or injure themselves amid the debris.
 
Photo from Sheridan County Conservation District